![](https://imgsa.baidu.com/forum/w%3D580/sign=e1c0551671f40ad115e4c7eb672d1151/bf4210f41bd5ad6e367f06c48bcb39dbb7fd3cf7.jpg)
![](https://imgsa.baidu.com/forum/w%3D580/sign=a48af84ff9deb48ffb69a1d6c01e3aef/ba9365cb0a46f21fe7793c7dfc246b600c33ae2c.jpg)
![](https://imgsa.baidu.com/forum/w%3D580/sign=23b6f0f1c41b9d168ac79a69c3dfb4eb/fd0b8622720e0cf382ba2cd50046f21fbe09aa2c.jpg)
![](https://imgsa.baidu.com/forum/w%3D580/sign=cea937472f2dd42a5f0901a3333a5b2f/734e9482b9014a90ef802493a3773912b31bee3f.jpg)
![](https://imgsa.baidu.com/forum/w%3D580/sign=7d8c7830b3389b5038ffe05ab535e5f1/34b7236d55fbb2fb084b3a3c454a20a44623dc11.jpg)
![](https://imgsa.baidu.com/forum/w%3D580/sign=806f162a9d0a304e5222a0f2e1c9a7c3/fe4aae7eca80653871a7c63d9ddda144ad34822c.jpg)
![](https://imgsa.baidu.com/forum/w%3D580/sign=4b7a2c9794510fb37819779fe932c893/9d4624292df5e0fe3492eb2f566034a85fdf72eb.jpg)
人民网南昌5月2日电(时雨)
串联了南昌西站、红谷滩的南昌地铁2号线首通段的施工进度备受市民关注,2日,喜讯传来,继热滑试验及信号调试工作完成之后,首通段(地铁大厦站至南路站段)空载试运行已启动。
据介绍,空载试运行是由建设转向运营的过渡阶段,是试运营的预演,也是地铁开通试运营前必经的环节。此次空载试运行分四个阶段,第一阶段为双车电话闭塞法行车及系统功能操作;第二阶段为四车套跑及非正常应急处置演练;第三阶段为八车套跑及非正常应急处置演练;第四阶段为按运行图套跑。按照上线列车逐步增加、发车间隔逐步缩小的原则开展试运行的同时,联调期间还将穿插极端情况下功能验证和模拟故障演练,以确保开通试运营时运营有序。空载试运行共计三个月。
据悉,南昌地铁在开通试运营前,从编制试运行总体方案到各阶段的组织方案,都严格按照《城市轨道交通试运营基本条件》要求执行,并将系统联调、故障演练、人员培训等工作融入到试运行工作中,以提升人机磨合程度。目前,2号线人员需求及补充计划已完成,各岗位人员均已调配到位,按照“新老搭配,以老带新”原则,积极开展人员上岗技能鉴定及岗前培训等工作,并完成上岗资格鉴定取证。
据悉,2号线首通段串联了南昌西站、红谷滩中心区等主要的客流集散点,与1号线连接,实现换乘功能。届时,客运转换将更加便捷,地铁线的客流吸引能力也将大大增强。